Afghanistan’s Islamic Emirate says work on the TAPI Pipeline is advancing steadily, with major infrastructure activities continuing at a rapid pace across the country.
Zabihullah Mujahid said around 130 kilometers of the route have been leveled so far, while 91 kilometers of pipeline have already been installed.
He said the total distance from the border of Turkmenistan to the Herat Industrial Park covers 153 kilometers, where the pipeline will extend.
According to Mujahid, completion of the project is expected to bring major economic transformation to Herat, with thousands of factories projected to become operational.
The 1,814-kilometer pipeline, including 816 kilometers passing through Afghanistan to Pakistan, is designed to transport 33 billion cubic meters of gas annually. Work on the Afghan section began in September 2024, with 52 percent completed so far, while the Herat section is expected to be finished by the end of 2026.
Once operational, the project is expected to provide Afghanistan with millions of dollars in annual transit revenue, while the country will also receive 500 million cubic meters of gas initially, increasing to 1 billion and later 1.5 billion cubic meters in future phases.